Ms project gantt chart remove year line
Ms project gantt chart remove year line












The task starts on or before a specific date. The task finishes on or after a specific date. The task starts on or after a specific date.

ms project gantt chart remove year line

This is the default constraint when you schedule from the project start date. This is the default constraint when you schedule from the project finish date. The task starts as late as it can without delaying other tasks. Inflexible constraints, which have specific start or finish dates. Semi-flexible constraints, which include earliest start dates or latest finish dates. Those constraints come in three flavors:įlexible constraints, which don’t tie a task to a specific date. With Project, you can add eight different constraints to tasks. If your project is scheduled from the start date, choose As Soon As Possible. If your project is scheduled from the finish date, choose As Late As Possible.

ms project gantt chart remove year line

In the Constraint type list, pick one of these options: You can’t technically remove a constraint, but you can reset it to the default value, tying it to other tasks rather than to a specific date. Set task durations yourself and create links between tasks, and then Project will calculate the task start and finish dates.

ms project gantt chart remove year line

Project management tip Let Project do what it does best - schedule your project. If you pick a constraint other than As Late As Possible or As Soon As Possible, add a date to the Constraint date box. Pick an option from the Constraint type list. On the Gantt Chart task list, double-click the task. If you have an unavoidable constraint, such as an event date, pick the constraint type as well as the date: